Hilti Firestop Systems
Page: 2 of 3
1. CONCRETE FLOOR ASSEMBLY: 2 hour rated concrete floor assembly made from either lightweight or normal weight concrete with a
density of 100 to 150 pcf, having a min. thickness of 6 in. at the joint face. When a longitudinal recess (blockout) is required to contain an
architectural joint system, increase concrete floor assembly thickness to maintain a min. thickness of 6 in. and accommodate depth of
blockout formed in the concrete: blockout width unrestricted.
2. CURTAIN WALL ASSEMBLY: The curtain wall assembly shall incorporate the following construction features:
A. Mounting Attachment (Not Shown) - Attach aluminum framing (Item 2B) to the structural framing according to the curtain wall
manufacturer's instructions. Connect the mounting attachments to the joint face of the concrete floor assembly (Item 1) according to the
curtain wall manufacturer's instructions.
B. Aluminum Framing - Use hollow rectangular aluminum extruded tubing with min. overall dimensions of 0.100 in. thick, 4 in. high and 2-1/2
in. wide. Locate mullions (vertical aluminum framing) min. 60 in. on center (oc).  Locate the upper transom (horizontal aluminum framing)
such that the bottom surface of the transom is at the same height as the top surface of the floor assembly. For the spandrel region, the
lower transom (horizontal aluminum framing) must be spaced a minimum of 6 in. below the concrete floor as measured from the underside
of the floor to the top side of the transom.
C. Glass Panels - Sized and installed into aluminum framing (Item 2B) in accordance with the curtain wall manufacturer's instructions. Use
min. 1/4 in. thick, clear, heat strengthened (HS) or tempered glass with a max. width and height less than the aluminum framing (Item 2B)
oc spacing. OC spacing shall allow glass to be secured to the aluminum framing (Item 2B) between the notched shoulders.  Secure glass
panels with a thermal break (rubber extrusion), pressure bar (aluminum extrusion), min. 1/4-20 × 5/8 in. long screws, and a snap face
(aluminum extrusion).
D. Aluminum Anchor Brackets (Not Shown) - Use min. 1/2 in. thick aluminum anchor brackets to serve as part of the mounting attachment
(Item 2A) rigidly secured to the aluminum framing (Item 2B) and the concrete floor assembly (Item 1).
E. Sheet Metal Pan - Attach a fabricated 18 GA galvanized or plain steel box pan, 6 in. high and 3 in. deep composed of two L-shaped
sections to the aluminum framing with No. 10 self-drilling sheet metal screws at 12 in. oc along the top, and with four No. 10 self-drilling
sheet metal screws at each vertical end (two installed at the top and two at the bottom).  Install a bead of Hilti CFS-S SIL GG Firestop
Silicone on the underside of the horizontal member prior to installation of the 3 in. × 6 in. 18 GA steel box pan.  This box pan shall create a
cavity that is 3 in. deep and 6 in. tall underneath the aluminum member to house the curtain wall insulation (Item 2F). The box may be
fabricated by either method below:
a). An 18 GA galvanized or plain steel angle is attached to the underside of the aluminum framing.  The angle shall be formed such that
it has a 3 in. leg and a 6 in. leg, with the 3 in. leg attached to the aluminum framing.  A second 1 in. × 3 in. 18 GA galvanized or plain
steel angle is attached to the first with the 1 in. leg secured to the 6 in. leg of the first angle with No. 10 self-drilling sheet metal screws,
spaced 12 in. oc.  The 3 in. portion of the 3 in. × 1 in. angle is to be sized such that a 6 in. leg can be bent and formed into a vertical
leg at the ends to secure the angle to the vertical framing members on each side.
b). (Not Shown) An 18 GA galvanized or plain steel angle is attached to the underside of the aluminum framing.  The angle shall be
formed such that it has a 3 in. leg and a 1 in. leg, with the 3 in. leg attached to the aluminum framing.  The 3 in. portion of the 3 in. × 1
in. angle is to be sized such that a 7 in. leg can be bent and formed into a 6 in. vertical leg, to secure the angle to the vertical framing
members on each side, with a 1 in. horizontal flange at the bottom ends.  A second 6 in. × 3 in. 18 GA galvanized or plain steel angle
is attached to the first with the 6 in. leg secured to the 1 in. leg of the first angle with No. 10 self-drilling sheet metal screws, spaced 12
in. oc along the 1 in. leg and with at least one No. 10 self-drilling sheet metal screw at each end, secured to the 1 in. flange on the
vertical legs of the first angle.
F. Curtain Wall Insulation - Fill the cavity of the metal pan (Item 2E) with nominal 3 in. thick, min. 6 in. tall, 8 pcf density, mineral wool batt
insulation. Tightly fit, compress at least 1/8 in. in all directions. Use only Intertek certified products meeting the above min. requirements.
G. CURTAIN WALL INSULATION - Friction fit nominal 2 or 3 in. thick, 8 pcf density, mineral wool batt insulation in the area below the sheet
metal pan flush with the front surface of the mullions. Tape all adjacent edges between curtain wall insulation, or between aluminum
framing (Item 2B) and curtain wall insulation, with pressure sensitive aluminum foil tape, centered over the seam.  Use only Intertek
certified insulation products meeting the above min. requirements.
Reproduced by HILTI, Inc.
Courtesy of  Intertek Group
December 21, 2018
HI/BPF 120-15
Design No. HI/BPF 120-15